One of the most powerful tools that can be used when applying Lean Six Sigma is a Project Charter. In this article, we explain what a Project Charter is, how to apply it in a lean way, and we help you get started with a Project Charter template and a Project Charter example. After reading this blog, you will be able to start your Lean Six Sigma project with a strong foundation.
Supporting Lean Six Sigma with a Project Charter looks like this: with a short but powerful project document, the rationale, problem, objectives, scope, and roles are defined. From this foundation, any Lean Six Sigma project can be approached effectively. You can see a Project Charter as a project agreement between all stakeholders. It records why the project was initiated, what must be achieved, and how the organization will measure success. Within Lean Six Sigma, the DMAIC method is commonly used. In the first phase of this method (the Define phase), a Project Charter is usually created immediately. This ensures that everyone enters the project with the same expectations and that data is collected with the same goal in mind. Working lean without a Project Charter is risky: you miss the foundation needed to stay focused together throughout the project.
Lean projects that start without clear direction often get stuck. Teams work past each other, objectives remain too broad, or solutions are proposed without a clear understanding of the real problem. Especially in production environments where multiple departments and processes exist, miscommunication can arise quickly. Projects with a well-written Project Charter gain a significant advantage through the following benefits:
If you aim for clarity, focus, and measurability, there are five essential components that must be included in your Project Charter. Below, we discuss these five building blocks to correctly create a Lean Six Sigma Project Charter.
The problem statement describes what is going wrong and why this is a problem for the organization. At this stage, it is not about solutions, but about a factual, measurable description of the current situation. A good problem statement includes data (such as percentages, quantities, or financial impact) and is formulated objectively. This makes clear why this project should be a priority.
The objective shows what the project must deliver concretely. In a Lean Six Sigma Project Charter, this is always formulated SMART: Specific, Measurable, Achievable, Relevant, and Time-bound. The objective forms the basis for evaluation at the end of the project. By comparing the objective with the results, it can be determined whether the project was successful.
In the scope, you define the boundaries of the project. Which processes, lines, teams, and products fall under the project, and which can be excluded? This prevents a project from expanding uncontrollably. Especially in factory environments where processes are highly interconnected, a clear scope helps maintain focus.
A Lean Six Sigma Project Charter also needs to specify who is involved in the project. The allocation of roles is important here. Examples of roles include project leader, data analyst, production staff, or operators. By assigning roles upfront, ambiguities and discussions at a later stage can be avoided.
In a Project Charter for Lean Six Sigma projects, it is determined in advance how progress and success will be measured. KPIs are often established for this purpose, such as cycle time, OEE, or the number of complaints per batch. In addition to KPIs, critical success factors can be included, such as operator engagement, data availability, or cooperation from maintenance.
Looking for a simple Project Charter template for your Lean Six Sigma project? You can use the template below as a basic framework and expand it as needed.
Project Charter Template
Tips for filling out the template:
The Project Charter example below shows what a completed document could look like for a factory dealing with excessive changeover times.
Project name:
Reduce changeover time on Packaging Line B.
Problem statement:
The changeover time on Packaging Line B currently averages 52 minutes per changeover, while the standard is 35 minutes. As a result, 1–2 scheduled production runs are missed daily, leading to lower output and additional overtime. Longer changeover times also cause more stress for operators and disruptions in scheduling.
Objective:
Reduce the average changeover time on Packaging Line B from 52 to 35 minutes before November 1.
Scope – Inclusions:
Scope – Exclusions:
Project team and roles:
Critical success factors:
KPIs:
Deadlines / Milestones:
Even though a Lean Six Sigma Project Charter may seem simple, mistakes are often made that cost a lot of time later. The most common pitfalls include:
Avoiding these pitfalls increases the likelihood that a project will be completed on time and with good results.